Al-Youssifiyah Thermal Power Station — 840 MW
The Al-Youssifiyah Thermal Power Plant, with a capacity of 840 MW, was implemented at Al-Youssifiyah city south of Baghdad with the Russian company TechnoPromExport.
Scope of works
- Civil and construction works — Al Watan Al Arabi Co.
- Construction and erection of equipment — Al Said Group Co. for Electro-Mechanical Contracts
- Supply of materials — Al-Said International Group Co.
- Steel structures, ducts and large-diameter pipework
- Transport and installation of main transformers
- Quality assurance with X-ray and ultrasonic testing
Delivery
Al Watan Al Arabi's quality and commitment during the contracted assignments led TechnoPromExport to award it the management of the project. When the Russian company left Iraq because of the security situation, the works continued without interruption.
Thousands of skilled workers and qualified engineers carried out the works, with testing of materials and welds under the supervision and witness of an independent third-party testing company contracted by the Ministry of Electricity. The works were executed to a high standard and handed over to the Russian company, the Iraqi Directorate of the Al-Youssifiyah Project and the Iraqi Ministry of Electricity, in compliance with the project specification.